Present Status
Total Work Completed
0%
Access Road
100%
Camp
100%
Construction Power
100%
Headworks(Diversion, Intake, Settling Basin etc)
100%
Hydromechanical Works
97%
Water Convenience System
95%
Electro Mechanical Works
82%
PowerHouse(Civil Only)
100%
Switchyard and Substation
86%